Virginia-Class Submarines Late & Over Budget
that matters most
Get the latest maritime news delivered to your inbox daily.
Admiral Vern Clark, during hearings before the U.S. Senate Armed Services Committee last week, said that unanticipated labor issues at General Dynamics Electric Boat yard and "first of class construction issues" are to blame for the cost for SSN-774. Budget shortfalls are estimated at $42 million, and the delivery date has slipped from June to October 2004.
Similar issues have also beset SSN-775, but construction of this boat has been hampered by the fact that submarines have not been built at the Northrop Grumman Newport News shipyard in more than a decade. The total government project shortfall for this sub is estimated at $141.5 million, and the delivery date has been pushed back six months.