Salvage Operation Pulls Final Section of MSC Baltic III Ashore in Canada

salvage of grounded containership MSC Baltic III
Final section of the hull of MSC Baltic III being hoisted on to shore (Canadian Coast Guard)

The Canadian Coast Guard and Resolve Marine reported on November 27 that the final section of the wrecked containership MSC Baltic III has been pulled ashore. The pulling and removal of the hull sections of the vessel took approximately four months.

The pulling operation had begun on July 31 after earlier phases removed the accommodation block, cargo hatches, and cargo gear. Upper portions of the hull were also removed and taken away by barge for the recycling operation. Large chain pulls were used to move the vessel forward and then bring sections ashore to be cut up and trucked away for recycling.

The operation removed approximately 11,000 tons from the hull of the 679-foot (207-meter) vessel.  The Coast Guard highlights that the operation also included removing all 472 containers, including those containing dangerous goods, and approximately 1,700 metric tonnes of bulk fuel from the wreck, along with residual fuel recovered during tank-cleaning operations.

After four months, the final hull section was pulled on to the shore (Canadian Coast Guard)

It was a highly successful operation that resulted in only minimal amounts of pollution, which were quickly cleaned up during the salvage operation. The Coast Guard says while the threat of pollution will remain until the final portion of the wreck has been fully dismantled and removed from the shoreline, significant progress has been made toward eliminating the risk of pollution to the marine environment.

The 33,767-dwt vessel had blacked out during a storm on February 15, 2025, while approximately 12 miles offshore from Newfoundland. It was driven ashore in a remote cove, Cedar Cove, west of Corner Brook. In a daring operation, the 20 crewmembers were hoisted by helicopter without injury.

The last section will be cut in smaller pieces and trucked away for recycling (Canadian Coast Guard)

During the first phase of the salvage operation in 2025, the containers were mostly removed from the ship, and the fuel tanks were pumped. Severe winter weather sent waves crashing over the ship and caused several fractures in the hull.

With the last portion of the MSC Baltic III pulled ashore, the team is prepared for the cutting and removal operations. 

The next phase of the operation is site remediation. This work is scheduled to begin in 2027.